<-   Realization of CoRoT   ->

Decision

In October, 2000, the comittee of the CNES scientific programs selected CoRoT as the third mission of the PROTEUS chain, with a launch planned in 2004.

figures/champagne.jpg

CNES cost : about 60 billion euros

  • + 50 CNES/CNRS engineers ( for 5 years)
  • + 150 to 200 scientists.

The French "leadership " is preserved!

However, we had to be quick, catch up with making decisions.... New European and Brazilian partners joined the project.

Realization

The elementary building blocks of the instrument had been realized by industrialists and laboratories. After verification, they were gradually put together. At each step, function tests and performance control tests were undertaken.

figures/Cam-complete_IAS.jpg

At the same time, the platform was realized by ALCATEL in Cannes, France. Finally, the instrument and the platform were assembled in 2005.

After numerous checks, the satellite was delivered at the end of 2005 to the industrialist who carried out its launch in 2006.